OUTAGE RESOLUTION: North Campus Power Outage - 2013/07/08

What happened?
North Campus experienced scattered power outages.

Who was affected?
Some North Campus users were affected by this outage.

What was the impact?
The affected users were not able to use any computer systems without backup power causing some IT services to be unavailable.

What was the timeline of the incident?
Start: 2013/07/08 15:45 - IT support analysts discovered a problem with power to campus.
2013/07/08 15:55 - IT support analysts began working on the issue.
End: 2013/07/08 16:05 - Power was restored and the affected IT services came back on line.